Typical Lot Description
 

ACREAGE
Total Acres:
Typical Lot Size:
Percent Available: 

210
18
100%

UTILITIES
Electricity
Current: 



2 bus substation, 125 kv
Proposed: Feeder lines along east and north boundary
Gas
Current:

16" high-pressure along east boundary
Proposed: 6" along north and west boundary line
Sewer
Current:

90" along east boundary
Proposed: 10" along south boundary
Water
Current: 

20" main along east boundary
Proposed:  12" along north and west boundary

ROAD ACCESS
      Current: 


4 lane with center turn lane along east boundary line
      Proposed:  4 land along north and west boundary line

MAJOR CONNECTING INTERSTATES: 

Interstates 40 & 55

DISTANCE TO AIRPORT: 

12.6 miles

STORM DRAINAGE
      Current: 


Natural
      Proposed: Open ditch or curb and gutter

RAIL ACCESS
      Current:


1,000 yards north of area
      Proposed: 115 lbs. along southern boundary

RAIL CONNECTIONS
      Direct Access: 


CN
      Indirect Access: BNSF, CSX, NS, UP

TYPICAL ELEVATION
      Low:


210'
      High: 220' (Levee protected top elevation 235)

SOIL TYPES: 

Silt Loam, Silty Clay, Fine Sandy Loam

PRICING POLICY: 

Please contact the Port Commission office

PHOTO

 

Contact Memphis Light, Gas and Water for detailed information on line locations and capabilities at 901-544-6549. For sewer line issues contact City of Memphis Engineering Department, Sewer Design at 901-576-6951. For the location of underground utilities dial 800-351-1111.

return to overview map

 